Mesa Ridge High School Addition

Education · 2023

Mesa Ridge High School Addition

A career and technical education wing plus a renovated commons, built entirely around the school calendar.

All projects
Client
Poudre Valley School District
Location
Fort Collins, CO
Size
74,000 sq ft
Duration
19 months
Delivery
General contracting

Scope of work

  • Structural addition
  • CTE shop fit-out
  • Commons renovation
  • Fire and life safety upgrade

The challenge

Loud and disruptive work could only happen during summer break and after hours, and the building had to be fully code-compliant and occupiable every August.

Our approach

We front-loaded demolition and structural work into an 11-week summer window, staged materials off site, and ran a second shift through the school year for finishes behind temporary partitions.

The outcome

Two consecutive school years opened on time with no displaced classrooms. The CTE wing was handed over with equipment installed and tested.