Education · 2023
Mesa Ridge High School Addition
A career and technical education wing plus a renovated commons, built entirely around the school calendar.
All projects
- Client
- Poudre Valley School District
- Location
- Fort Collins, CO
- Size
- 74,000 sq ft
- Duration
- 19 months
- Delivery
- General contracting
Scope of work
- Structural addition
- CTE shop fit-out
- Commons renovation
- Fire and life safety upgrade
The challenge
Loud and disruptive work could only happen during summer break and after hours, and the building had to be fully code-compliant and occupiable every August.
Our approach
We front-loaded demolition and structural work into an 11-week summer window, staged materials off site, and ran a second shift through the school year for finishes behind temporary partitions.
The outcome
Two consecutive school years opened on time with no displaced classrooms. The CTE wing was handed over with equipment installed and tested.
Gallery
On site



Building something like this?
Tell us about your site, your program and your deadline. We will put a real number and a real schedule in front of you.