Cheyenne Distribution Center

Industrial · 2024

Cheyenne Distribution Center

A 640,000 square foot tilt-up distribution facility with 40-foot clear height and full automation infrastructure.

All projects
Client
Continental Logistics
Location
Cheyenne, WY
Size
640,000 sq ft
Duration
14 months
Delivery
Design-build

Scope of work

  • Mass grading
  • Tilt-up panels
  • Super-flat slab
  • Dock equipment
  • Conveyor infrastructure

The challenge

The owner needed the building racked and operating before peak season, which left fourteen months from ground-breaking to first pallet on a site with expansive soils and a short pour window each winter.

Our approach

We over-excavated and moisture-conditioned the pad before frost, cast panels on the slab in two staged lifts, and used heated enclosures to keep the super-flat floor pours going through January.

The outcome

Certificate of occupancy issued 11 days early. Floor flatness measured F50 across the racked area, well above the specified tolerance.