Civil · 2022
Clear Creek Bridge Replacement
Replacement of a two-span arterial bridge with staged traffic maintained throughout construction.
All projects
- Client
- Jefferson County Public Works
- Location
- Golden, CO
- Size
- 340 linear ft
- Duration
- 13 months
- Delivery
- General contracting
Scope of work
- Demolition
- Drilled shafts
- Precast girders
- Approach work
- Stream bank restoration
The challenge
The crossing carried 24,000 vehicles a day and could not be fully closed, and in-stream work was restricted to a narrow window outside the trout spawning season.
Our approach
We built the bridge in two halves under a head-to-head traffic shift, drilled shafts from a temporary work platform, and completed all in-water activity inside the 90-day environmental window.
The outcome
Opened to full traffic five weeks early with no unscheduled closures and no environmental violations recorded.
Gallery
On site



Building something like this?
Tell us about your site, your program and your deadline. We will put a real number and a real schedule in front of you.